Renovation Handover Checklist – Snag List, Documents and Warranty
Renovation

Renovation Handover Checklist – Snag List, Documents and Warranty

An apartment renovation does not end with the last coat of paint – it ends with the handover. That is when you inspect the finished work, when the snag list goes on paper, and when the warranty period starts.

An apartment renovation does not end with the last coat of paint – it ends with the handover. That is when you inspect the finished work, when the snag list goes on paper, and when the warranty period starts. Here is how a handover works at the end of a full apartment renovation, what to check room by room, and which documents you should receive.

Most renovation guides cover planning and construction; few cover the finish. Yet the handover is the day you find out whether the flat is truly ready to move into, and whether the small defects come with a clear, dated commitment to fix them.

Summary

  • The handover is a joint walk-through recorded in a signed protocol, with a snag list and repair deadlines attached.
  • Under the Hungarian Civil Code, acceptance cannot be refused over a defect whose repair does not prevent normal use. Such defects go on the snag list.
  • For defects that prevent use or affect safety (leaks, heating that does not work, faulty electrics), acceptance can be postponed until they are fixed.
  • You should receive the keys, warranty cards, manuals, test reports and a record of the meter readings.
  • Warranty and statutory liability for defects are two different rights. Agree the contractor's warranty period in the contract.
  • The final invoice is tied to the handover; parties often agree a retention until snag items are completed.

What is the handover?

The handover is the procedure in which the contractor presents the finished work and the client checks it against the contract and the itemised budget. Two rules from Section 6:247 of the Hungarian Civil Code are worth knowing.

  • Minor defects do not block acceptance. If repairing a defect does not prevent normal use, the work must be accepted and the defect listed.
  • Moving in can count as acceptance. If the client skips the handover but takes possession, the legal effects of performance apply from that point.

A good handover is not a hunt for faults – it is a shared inventory of what is finished and what is still to come.

How the handover runs

StepWhat happensTip
1. Completion noticeThe contractor reports the apartment renovation complete and you agree a dateInspect after cleaning, in daylight
2. Walk-throughRoom by roomBring the budget and drawings
3. TestsTaps, drains, heating, sockets, lights, windowsTry every tap and every switch
4. ProtocolDate, participants, meter readings, documents handed overBoth parties sign
5. Snag listItemised, by room, with deadlinesPhotograph each item
6. Follow-up visitChecking the snag itemsClose it in writing

Allow two to three hours for an average flat.

Room-by-room checklist

Every room

  • Paint: even coverage, no streaks, stains or cracks at corners and ceiling joints.
  • Floors and tiles: no hollow, loose or damaged pieces; even grout lines; skirting fixed.
  • Interior doors: open freely, latch and lock work.
  • Windows: close properly, tilt-and-turn hardware runs smoothly, seals intact.
  • Sockets and switches: all work, cover plates straight.

Bathroom and WC

  • Hot and cold work on every tap; connections are dry.
  • Drains clear quickly; no standing water around the shower or bath.
  • Silicone joints continuous; cistern does not leak.
  • Ventilation works; the circuit has residual-current protection.

Kitchen

  • Appliances connected and working; nothing drips under the sink.
  • Worktop joints sealed; doors and drawers adjusted.

Heating and electrics

  • Every radiator or loop heats up; the thermostat switches.
  • Circuits in the consumer unit are labelled; the RCD test button trips.
  • For gas appliances, the commissioning report is on file.

The snag list: what can wait and what cannot

Type of defectExampleWhat to do
Cosmetic, does not prevent usepaint mark, door needing adjustmentAccept, list, set a deadline
Missing itemlight not fitted, door delivered lateAccept, set a deadline, proportionate retention
Prevents useheating not working, bathroom unusableAcceptance can wait until fixed
Safetywater or gas leak, faulty electrical protectionImmediate repair, no acceptance until then

Documents you should receive

  • Handover protocol with the snag list and meter readings.
  • Warranty cards and manuals for appliances, boiler, air conditioning, sanitary ware, windows.
  • Electrical test report, if the wiring was replaced or extended.
  • Gas documentation and commissioning report, if gas was involved.
  • Details of installed materials: tile type and batch, paint colour codes, grout colour.
  • Photos of concealed pipes and cables taken before tiling.
  • Invoices and the final account against the itemised budget, including extras.
  • Keys, remotes, codes.

Warranty and liability for defects in Hungary

The key difference is the burden of proof: under a warranty the contractor must prove the defect arose after handover; under statutory liability for defects it is, as a rule, the client who must prove the defect.

RightApplies toPeriod (as of November 2026)
Statutory liability for defects (Civil Code)Any defective performance, even without a contract clause2-year limitation in consumer contracts; 5 years where the contract concerns real property
Mandatory warranty for repair and maintenance services (Gov. Decree 249/2004)Home repair and maintenance services to consumers above HUF 20,0006 months
Mandatory warranty for new homes (Gov. Decree 181/2003)Newly built homes3, 5 or 10 years by structure – does not cover renovations
Contractual warrantyWhatever the contractor undertakesPer the contract
Manufacturer's warrantyAppliances, fittings, windowsPer the warranty card

In practice: agree the warranty period for the apartment renovation in the contract, trade by trade, because the statutory mandatory warranty for renovation work is short. This article is general information, not legal advice.

Apartment renovation in Budapest with a written handover

M&M TeleHome delivers full apartment renovation in Budapest and Pest County as general contractor. Every project starts with an itemised budget and closes with a written handover, a snag list and a document pack – with an English-speaking contact.

Frequently asked questions

Can I refuse acceptance if I find a defect?

Not for a minor defect that does not prevent use: the work is accepted and the defect goes on the snag list with a deadline. If the flat cannot be used normally or there is a safety risk, acceptance can wait until the repair.

How long is the warranty on an apartment renovation?

Statutory liability for defects applies without any contract clause. The mandatory warranty for home repair services to consumers is 6 months, so a longer warranty should be agreed in the contract. Installed appliances carry the manufacturer's warranty.

Should I move in before the handover?

We advise against it. Taking possession can legally count as acceptance, and after moving in it is harder to tell a construction defect from wear.

What if a defect appears after the handover?

Report it to the contractor in writing, with photos, as soon as you notice it. Within the warranty or liability period you can ask for a repair.

Related articles in English: How to prepare a renovation · Panel apartment renovation in Budapest · Why most apartment renovations in Budapest go wrong at the start

Sources: Act V of 2013 (Civil Code) – National Legislation Database · Gov. Decree 249/2004 · Gov. Decree 181/2003

Request a quote

Request a no-obligation quote

On-site survey, itemised cost estimate, fixed deadline and warranty – we reply within 1 business day.

  • Reply within 1 business day
  • Itemised cost estimate
  • Fixed price, fixed deadline, warranty
No obligationMon–Fri 8:00–18:00 · info@telehome.hu