Renovation Handover Checklist – Snag List, Documents and Warranty
An apartment renovation does not end with the last coat of paint – it ends with the handover. That is when you inspect the finished work, when the snag list goes on paper, and when the warranty period starts.
An apartment renovation does not end with the last coat of paint – it ends with the handover. That is when you inspect the finished work, when the snag list goes on paper, and when the warranty period starts. Here is how a handover works at the end of a full apartment renovation, what to check room by room, and which documents you should receive.
Most renovation guides cover planning and construction; few cover the finish. Yet the handover is the day you find out whether the flat is truly ready to move into, and whether the small defects come with a clear, dated commitment to fix them.
Summary
- The handover is a joint walk-through recorded in a signed protocol, with a snag list and repair deadlines attached.
- Under the Hungarian Civil Code, acceptance cannot be refused over a defect whose repair does not prevent normal use. Such defects go on the snag list.
- For defects that prevent use or affect safety (leaks, heating that does not work, faulty electrics), acceptance can be postponed until they are fixed.
- You should receive the keys, warranty cards, manuals, test reports and a record of the meter readings.
- Warranty and statutory liability for defects are two different rights. Agree the contractor's warranty period in the contract.
- The final invoice is tied to the handover; parties often agree a retention until snag items are completed.
What is the handover?
The handover is the procedure in which the contractor presents the finished work and the client checks it against the contract and the itemised budget. Two rules from Section 6:247 of the Hungarian Civil Code are worth knowing.
- Minor defects do not block acceptance. If repairing a defect does not prevent normal use, the work must be accepted and the defect listed.
- Moving in can count as acceptance. If the client skips the handover but takes possession, the legal effects of performance apply from that point.
A good handover is not a hunt for faults – it is a shared inventory of what is finished and what is still to come.
How the handover runs
| Step | What happens | Tip |
|---|---|---|
| 1. Completion notice | The contractor reports the apartment renovation complete and you agree a date | Inspect after cleaning, in daylight |
| 2. Walk-through | Room by room | Bring the budget and drawings |
| 3. Tests | Taps, drains, heating, sockets, lights, windows | Try every tap and every switch |
| 4. Protocol | Date, participants, meter readings, documents handed over | Both parties sign |
| 5. Snag list | Itemised, by room, with deadlines | Photograph each item |
| 6. Follow-up visit | Checking the snag items | Close it in writing |
Allow two to three hours for an average flat.
Room-by-room checklist
Every room
- Paint: even coverage, no streaks, stains or cracks at corners and ceiling joints.
- Floors and tiles: no hollow, loose or damaged pieces; even grout lines; skirting fixed.
- Interior doors: open freely, latch and lock work.
- Windows: close properly, tilt-and-turn hardware runs smoothly, seals intact.
- Sockets and switches: all work, cover plates straight.
Bathroom and WC
- Hot and cold work on every tap; connections are dry.
- Drains clear quickly; no standing water around the shower or bath.
- Silicone joints continuous; cistern does not leak.
- Ventilation works; the circuit has residual-current protection.
Kitchen
- Appliances connected and working; nothing drips under the sink.
- Worktop joints sealed; doors and drawers adjusted.
Heating and electrics
- Every radiator or loop heats up; the thermostat switches.
- Circuits in the consumer unit are labelled; the RCD test button trips.
- For gas appliances, the commissioning report is on file.
The snag list: what can wait and what cannot
| Type of defect | Example | What to do |
|---|---|---|
| Cosmetic, does not prevent use | paint mark, door needing adjustment | Accept, list, set a deadline |
| Missing item | light not fitted, door delivered late | Accept, set a deadline, proportionate retention |
| Prevents use | heating not working, bathroom unusable | Acceptance can wait until fixed |
| Safety | water or gas leak, faulty electrical protection | Immediate repair, no acceptance until then |
Documents you should receive
- Handover protocol with the snag list and meter readings.
- Warranty cards and manuals for appliances, boiler, air conditioning, sanitary ware, windows.
- Electrical test report, if the wiring was replaced or extended.
- Gas documentation and commissioning report, if gas was involved.
- Details of installed materials: tile type and batch, paint colour codes, grout colour.
- Photos of concealed pipes and cables taken before tiling.
- Invoices and the final account against the itemised budget, including extras.
- Keys, remotes, codes.
Warranty and liability for defects in Hungary
The key difference is the burden of proof: under a warranty the contractor must prove the defect arose after handover; under statutory liability for defects it is, as a rule, the client who must prove the defect.
| Right | Applies to | Period (as of November 2026) |
|---|---|---|
| Statutory liability for defects (Civil Code) | Any defective performance, even without a contract clause | 2-year limitation in consumer contracts; 5 years where the contract concerns real property |
| Mandatory warranty for repair and maintenance services (Gov. Decree 249/2004) | Home repair and maintenance services to consumers above HUF 20,000 | 6 months |
| Mandatory warranty for new homes (Gov. Decree 181/2003) | Newly built homes | 3, 5 or 10 years by structure – does not cover renovations |
| Contractual warranty | Whatever the contractor undertakes | Per the contract |
| Manufacturer's warranty | Appliances, fittings, windows | Per the warranty card |
In practice: agree the warranty period for the apartment renovation in the contract, trade by trade, because the statutory mandatory warranty for renovation work is short. This article is general information, not legal advice.
Apartment renovation in Budapest with a written handover
M&M TeleHome delivers full apartment renovation in Budapest and Pest County as general contractor. Every project starts with an itemised budget and closes with a written handover, a snag list and a document pack – with an English-speaking contact.
- About us and our services (English page)
- Request a quote via our English page
Frequently asked questions
Can I refuse acceptance if I find a defect?
Not for a minor defect that does not prevent use: the work is accepted and the defect goes on the snag list with a deadline. If the flat cannot be used normally or there is a safety risk, acceptance can wait until the repair.
How long is the warranty on an apartment renovation?
Statutory liability for defects applies without any contract clause. The mandatory warranty for home repair services to consumers is 6 months, so a longer warranty should be agreed in the contract. Installed appliances carry the manufacturer's warranty.
Should I move in before the handover?
We advise against it. Taking possession can legally count as acceptance, and after moving in it is harder to tell a construction defect from wear.
What if a defect appears after the handover?
Report it to the contractor in writing, with photos, as soon as you notice it. Within the warranty or liability period you can ask for a repair.
Related articles in English: How to prepare a renovation · Panel apartment renovation in Budapest · Why most apartment renovations in Budapest go wrong at the start
Sources: Act V of 2013 (Civil Code) – National Legislation Database · Gov. Decree 249/2004 · Gov. Decree 181/2003
Request a no-obligation quote
On-site survey, itemised cost estimate, fixed deadline and warranty – we reply within 1 business day.
- Reply within 1 business day
- Itemised cost estimate
- Fixed price, fixed deadline, warranty
Related articles

Panel Apartment Renovation in Budapest – A Step-by-Step Guide
A panel apartment is more predictable to renovate than a hundred-year-old downtown flat, but it has its own rules: most walls are load-bearing, the risers are shared, and the wiring runs inside concrete.
Read more →
Renovating a Rental Apartment in Budapest – Where to Spend and Where Not To
Renovating a rental apartment follows a different logic from renovating your own home. The question is not what you like, but what pays back, what survives tenants, and how long the flat stands empty while the work is done.